Mangkolemba Multipurpose Hall row: CSO holds silent procession after ultimatum expires

schedule
2026-11-24 | 06:30h
update
2026-11-24 | 06:30h
person
mokokchungtimes.com
domain
mokokchungtimes.com

Organisation says govt has not responded to eight demands issued on October 3; warns of further agitation if grievances remain unaddressed

The Civil Society Organisation (CSO), Mangkolemba, on Monday held a silent procession as the first phase of public agitation over the Multipurpose Hall issue, following the expiry of a 30-day ultimatum issued to the Nagaland government.

CSO Mangkolemba members take part in a silent procession on Monday as the first phase of agitation over the Multipurpose Hall issue, following the expiry of a 30-day ultimatum to the state government.

In a formal intimation to Chief Minister Neiphiu Rio, routed through the Additional Deputy Commissioner (ADC), Mangkolemba, the organisation had said the stipulated period expired without the government fulfilling the eight demands raised in its October 3 ultimatum or communicating with the organisation regarding its grievances.

The silent procession was held in pursuance of Point 9 of the ultimatum, which outlined the organisation’s proposed course of action in the event that its demands remained unaddressed.

Advertisement

The CSO has warned that continued failure to address the demands would compel further courses of action as stipulated in the ultimatum.

The October 3 public meeting had adopted a set of resolutions calling for the government to resolve the controversy surrounding the Khelo India-funded Multipurpose Hall, including the demand that the facility be constructed at Mangkolemba town in accordance with what the organisation maintains are the project’s original official records.

The dispute centres on the location and official identity of the project, which was named Multipurpose Hall Mangkolemba but constructed at Longtho village under Mangkolemba Circle.

The Directorate of Youth Resources and Sports had earlier maintained that the project was executed at an approved geo-tagged location in Longtho village, based on the coordinates incorporated in the approved project documents. The department also stated that the location had been verified and the project certified as complete by a monitoring committee.

The CSO’s intimation, signed by convenor I Tia Jamir and secretary Wapongtoshi, had formally notified the government of the organisation’s decision to begin public agitation.

 

MT

Related Posts:

Advertisement

Imprint
Responsible for the content:
mokokchungtimes.com
Privacy & Terms of Use:
mokokchungtimes.com
Mobile website via:
WordPress AMP Plugin
Last AMPHTML update:
24.11.2026 - 06:40:10
Privacy-Data & cookie usage: