The Ao Baptist Arogo Mungdang (ABAM) has sought a “thorough, impartial, and time-bound examination” of the Rs 24.94 crore “Soulful Trails: The Impur Heritage Experience” project, raising concerns over the reported release of funds, absence of physical work at Impur, stakeholder consultation and a possible revision of the Detailed Project Report (DPR).

In a representation to the Chief Secretary of Nagaland, ABAM sought verification and administrative review of the release and utilisation of funds sanctioned for Impur under the Challenge-Based Destination Development (CBDD) component of the Swadesh Darshan scheme of the Ministry of Tourism, Government of India.

According to ABAM, an amount of Rs 6.06 crore was reportedly released or credited to the contractor, M/s Aren Enterprise, through the Public Financial Management System (PFMS) on August 21, 2025, and March 29, 30 and 31, 2026.

“However, ABAM has not observed any physical execution of work at Impur in connection with the said project to date,” the representation stated.

In view of the amount reportedly released, ABAM sought clarification on “the basis of these payments, the corresponding contractual milestones, the status of work, the verification and certification process followed, and the current financial and physical progress of the project.”

It also requested a detailed account of the sanctioned amount, funds released, expenditure incurred to date and the balance amount available.

The organisation raised questions over the preparation of the DPR, particularly whether a field visit and detailed assessment of the Impur Mission Centre were undertaken during the planning process.

The Impur Mission Centre, established by the first American missionary to Nagaland, Rev. Dr. E.W. Clarke, holds “immense historical, cultural, and religious significance, particularly in tracing the introduction and growth of Christianity in Nagaland,” the representation stated.

The project reportedly covers three zones: Zone I – Chungtiayimsen, Zone II – Impur and Zone III – Molungkimong.

ABAM said that, given Impur’s significance in the historical and heritage context of the project, it would like clarification on the proposed components, site allocation, scope of work and how the respective zones are integrated into the overall heritage and pilgrimage experience.

On stakeholder consultation, ABAM placed on record that, “to the best of its knowledge, no formal consultative meeting or coordination was held with ABAM officials at Impur in connection with the preparation or implementation of the project.”

It further stated that it was not aware of any field visit by officials of the Department of Tourism to Impur in connection with the project.

The organisation has accordingly sought clarification on consultations undertaken with local stakeholders, the site assessment conducted and the process followed in determining the project components and implementation requirements at Impur.

Another major concern raised by ABAM is the reported proposal by the Department of Tourism to revise the DPR, which may involve changes to the project components, including the possible removal of Impur or relocation of certain activities to another site.

ABAM sought clarification on whether such a proposal had been submitted to or was under consideration by the Ministry of Tourism, whether the State Government was aware of it, and the reasons and administrative circumstances necessitating such a revision at this stage.

The organisation also sought clarification on the sequence of events leading to the reported proposal, particularly in relation to the payments reportedly released during August 2025 and March 2026 and its representation submitted to the Director of Tourism on April 22, 2026.

“In the interest of transparency and clarity, it would be helpful to understand whether the proposed revision is based on technical considerations, administrative requirements, site-related issues, implementation constraints, or any other reasons, and how the interests and heritage significance of Impur have been considered in the process,” the representation stated.

ABAM said it came to know about the project following Rajya Sabha Unstarred Question No. 1413, answered on December 11, 2025, concerning the status of the Swadesh Darshan 2.0 scheme, including Impur, Nagaland, raised by Member of Parliament Smt. Mausam B. Noor.

“Prior to this, ABAM was not aware of the sanction and details of the said project,” it stated, adding that relevant stakeholders and local institutions connected with the heritage site should be appropriately informed and consulted regarding projects of this nature.

Upon learning about the project, ABAM said it submitted a letter dated April 22, 2026, to the Director of Tourism, Nagaland, requesting copies of the Concept Note and DPR.

The letter also sought clarification on stakeholder consultation, project objectives, implementation plans, funding structure, long-term sustainability and the procedural steps followed in the planning and implementation of the project.

However, ABAM said it had not received any acknowledgement or response to the representation to date.

To obtain a clearer understanding of the project and its implementation, ABAM constituted a committee to formally pursue the matter. It said the information presently available to the organisation, including details regarding the project and release of funds, had been obtained through two RTI applications submitted by the committee to the concerned Department.

The representation also raised questions concerning the financial procedures and contractual arrangements governing the payments made to the contractor. These include the applicable guidelines, contractual provisions, advance-payment arrangements, progress reports, certifications and supporting documents.

ABAM further sought clarification on how funds already released and existing contractual obligations would be dealt with in the event of a revision of the DPR or a change in the project location or components. It also asked whether any proposed revision would require fresh tendering or other procurement procedures, or whether the existing contractual arrangement would continue.

In its request for intervention, ABAM asked the Chief Secretary to direct the concerned Department to furnish a comprehensive status report covering the sanctioned amount, project components, funds released and utilised, balance funds, physical progress and implementation schedule.

It also requested an examination of the circumstances surrounding the preparation of the DPR, site assessment, stakeholder consultation, tendering, award of work and subsequent release of funds.

Among other requests, ABAM sought verification of the reported PFMS payments and supporting documents, clarification on the proposed DPR revision, and consideration of an independent administrative or financial review.

The organisation further urged the government to ensure that any further release of funds, revision of project scope, change of location or modification of contractual arrangements is undertaken strictly in accordance with applicable guidelines, financial rules, contractual obligations and approval of the competent authorities.

It also requested the preservation and availability of all relevant official records, including correspondence, tender documents, work orders, financial records and inspection reports, for verification by the competent authority.

ABAM said the representation was submitted “bona fide and in the larger public interest”, seeking to ensure administrative scrutiny, financial accountability, procedural compliance and adherence to the approved objectives and terms of sanction of the project.

“In view of the historical, cultural, and heritage significance of Impur,” the organisation urged that the matters raised be subjected to a “thorough, impartial, and time-bound examination” and that appropriate corrective, administrative or legal measures, as warranted by the findings, be initiated to safeguard public funds and uphold institutional accountability.

 

MT